Supreme Court Reinstates CERC Charges For Tuticorin Pooling Station Transmission Links
News2 min read

Supreme Court Reinstates CERC Charges For Tuticorin Pooling Station Transmission Links

L

LawWorld

Power Grid Corporation of India Ltd has got back the charges approved for two links at the Tuticorin Pooling Station. The Supreme Court in India, sitting with Justices J.B. Pardiwala and K. Vinod Chandran, allowed Power Grid's appeals, set aside the Appellate Tribunal for Electricity's orders and restored the Central Electricity Regulatory Commission's decision.

Justice K. Vinod Chandran wrote the judgment. It said the two links had carried electricity, so there was no need to reconsider the commercial operation dates cleared by the regulator.

The fight was over money for the gap before the generator's dedicated line was ready. Power Grid wanted tariff from the declared commercial operation of the pooling station links.

Moxie Power Generation Ltd, described in the proceedings as formerly Tamil Nadu Generation and Distribution Corporation Ltd, was held responsible as the generating company for the delay in its dedicated line.

The bench said the delay lay with the generator. The charges levied for the intervening period were justified.

Generator held responsible for delay

Power Grid had told the apex court that the tribunal should not have interfered with the regulatory approval. It sought restoration of the approved dates and related charges for the two links.

The court accepted that case. It said proof that electricity had actually flowed settled the question of use, leaving no ground to revisit the dates.

With the tribunal's interference gone, the regulator's determination applies again to the two links. Recovery linked to the declared dates stands revived.

For the intervening period, the bill stays with the generating company whose dedicated line was not ready. It does not fall on the network whose pooling station links were already carrying power.

The approved commercial operation dates continue to govern billing for the two links. Moxie Power remains liable for the charges tied to the delay in its own dedicated line, with the tribunal's orders set aside and no fresh reconsideration ordered.