A Bench of Justice Dipankar Datta and Justice Satish Chandra Sharma, in a judgment written by Justice Datta, allowed the appeals by Neycer (India) Ltd., formerly Neiveli Ceramics and Refractories Ltd., against GMB Ceramics Ltd. arising from objections under Sections 30 and 33 of the Arbitration Act, 1940 to an Umpire's award dated 23.06.1999.
The bench set aside a Calcutta High Court Division Bench judgment that had restored the Umpire's award of Rs 11,69,62,910 with 15% interest.
It restored the Single Judge's order restricting recovery to Rs 2 crore comprising Schedules 'A' and 'D' and part of 'E'.
The Court said the case turned on the jurisdiction of arbitrator as a creature of the contract and the reference.
It said an error within jurisdiction was different from an error in excess of jurisdiction, relying on Sudarsan Trading Co. v. State of Kerala, Associated Engineering Co. v. Government of A.P., and Bharat Coking Coal Ltd. v. Annapurna Construction.
The Division Bench had erred in treating the issue as a "plausible reading" of documents on merits, the Court held.
According to the bench, an umpire "cannot confer jurisdiction upon himself by misconstruing the terms of the reference".
Examining the pre-reference correspondence, the Court noted GMB had quantified its overrun claim at Rs 2 crore in telexes of August and September 1989.
On 06.10.1989 it wrote that "the matter boils down to our claim for overrun amount only".
Its telex of 19.10.1989 nominating its arbitrator described the reference as a claim of "over Rs. 2 crores" for all its losses.
The bench held a later letter of 24.10.1989, which only reserved rights on other claims, could not unilaterally enlarge the reference.
GMB's 1990 statement claiming Rs 8.82 crore, later amended to aggregate Rs 17.16 crore under six Schedules, therefore went beyond what had been referred, the Court said.
The Court distinguished Juggilal Kamlapat and State of Orissa v. Asis Ranjan Mohanty and rejected the Division Bench's subsidiary reasons.
It said Neycer's invocation letter was a notice calling on GMB to nominate its arbitrator.
Since Neycer had objected to claims beyond Rs 2 crore from the start, contesting them on merits was no waiver or acquiescence, the bench held.
Rs 3.5-Crore Brand Claim Rejected
On Schedule 'C', GMB had claimed Rs 3.5 crore as damages for being prevented from using the 'GMB-NEYCER' brand name.
The Umpire awarded Rs 2,03,43,000 on that Schedule on the basis of a single 1990 advertising agency estimate which no one from the agency proved.
Agreeing with the Single Judge, the Court found the award speculative, perverse and based on no evidence.
By 1999 the five-year period had expired, while GMB's own audited accounts showed actual advertising spending of only Rs 35,31,794, the bench noted.
It said the Umpire had used a "diametrically opposite yardstick" from the one he adopted while rejecting another Schedule built on anticipated expenditure.
On Clause 20, which says the consultants "shall endeavour to commission the plant within 18 calendar months" of sanction of the term loan, the Court found substantial force in Neycer's contention that it could not be made an underwriter of GMB's profits and loan interest for five years.
The Umpire himself found the delay was seven months, and the claim covered even a period when GMB's plant stayed closed for labour problems and power disconnection.
Neycer's wider argument that it bore no enforceable obligation would invite re-appreciation of evidence, the bench said.
It held the claims under the different Schedules were distinct and severable, relying on Upper Ganges Valley Electricity Supply Co. v. U.P. Electricity Board, so the valid part could survive after severing the excess.
Citing interim orders of 22.11.2018 and 07.01.2019, the Court recorded that Neycer had deposited Rs 2 crore as principal and Rs 2 crore as interest, which GMB withdrew in January 2019.
Both companies had undergone industrial sickness over nearly four decades, the bench observed.
It directed: "The said payment of Rs.4,00,00,000/- already received by GMB shall be treated as full and final satisfaction of the award as modified by the Single Judge (both towards principal and interest), and no further amount shall be recoverable by either party from the other under the award."
LawWorld Pro
Research, drafting and case management for the whole practice.
₹1,500 per month, or ₹12,000 per year — save 33%. 1 user, 250 active cases, 10 GB. Prices exclusive of 18% GST.
Comments
Sign in to read the discussion and share your thoughts.
Latest from LawWorld
News
View all- Supreme Court Protects Birbhum Stone Quarry Accused From Coercive Action Till December 521 Nov 2026
- Supreme Court Orders Medical Examination Of 70-Year-Old Convict In 1981 Dumka Double Murder21 Nov 2026
- Karnataka High Court Quashes Summoning Order Against Head Constable, Orders Fresh Process21 Nov 2026
- Karnataka High Court Upholds IGST Export Refund After Omission of Rule 96(10)21 Nov 2026
- Karnataka High Court Orders Police Protection for Play on Gandhi Assassination21 Nov 2026